TECHNICAL ASSESSMENT - PROPOSAL FOR CENTRAL AUSTRALIAN SOLAR/BATTERY MICROGRID
This Technical Report supports the Juwiriwiri Aboriginal Corporation's consideration of clean energy options for Ali Curung, a remote NT township of around 394 people, following a June 2026 grant under the Australian Government's First Nations Clean Energy Program, set against the backdrop of the NT's broader Territory Electricity Reform.

Project Scope and Activities
a) Initially considered a solar-battery microgrid: ~2MW solar, 1.5MW battery, genset backup, ~3 hectares, ~$1.8 million capital cost.
b) Identified a key constraint: NT legislation blocks connection to the Tennant Creek grid connection, and rooftop solar is difficult due to NT Government owned housing having restrictions.
c) options were negotiating behind the meter rooftop solar and batteries or standalone behind the meter off-grid system.
c) Compared governance and ownership models, including mutuals and cooperatives.
d) Examined how NT regulatory processes (PAIR Panel, RESIP) apply to the project.
e) Prepared early stage financial and economic benefits analysis.
The Milestone 1 assessment gives Ali Curung a clear technical foundation — system scale, cost, and the off-grid constraint — setting up decisions on ownership, funding, and delivery.